Loading...
007-0-29-P SR Public Utilities 01 Ballot REVIEWER: Tim Payseur Date: Feb. 14, 2007 VOTE: Conditionally Approve CONDITIONS: SHORT TERM: The professional engineer must submit three (3) sets of utility plans, engineer's report, and project specifications to HCDPU for review and subsequent approval. LONGE RANGE: The plans and associated documents must be approved by NCDENR- PWSS and all permits issued for the utility system improvements prior to construction. Once the state has issued all the necessary NCDENR permits for water, erosion control as well as the execution of the three party NCDOT Encroachment Agreement, then the utility contractor and professional engineer must schedule a pre-construction meeting with HCDPU prior to construction of said utility improvements. Page 2 of 2PUBLIC UTILITIES STAFF REPORT PUBLIC UTILITIES STAFF REPORT Harnett County, North Carolina Planning Department 108 E. Front Street, Lillington, NC 27546 Phone: (910) 893-7525 Fax: (910) 893-2793 Development Name: Haddon Pointe - 007-0-29 Property Description PIN(s): 0652-45-0519 Acreage: 28.60 acres Address/SR No.: Ballard Road (SR 1437) Water Public water is available for this development (via Harnett County) Comments: HCDPU has an existing four (4") inch water main located on Ballard Road that would not provide adequate fire flow for this project. the preliminary plans indicate that the developer intends to install a six (6") inch water line from the exisitng twelve (12") inch water main located on the north side of Harnett Central Road (SR 2215) to serve this development. If the six (6") inch water line must be extended more than 2,000 linear feet, then the developer should extend an eight (8") inch water line from the exisitng twelve (12") inch water main located on the north side of Harnett Central Road (SR 2215) to serve this development. Otherwise, the preliminary plat would be acceptable to HCDPU. NOTE: HCDPU provides this information as a curteousy to the developer, registered land surveyor and professional engineer for design purposes. However, HCDPU cannot be held liable for errors, mistakes, ommissions, and inaccurate information provided through this preliminary approval process. It is therefore recommended that the engineer or developer "field verify" the information provided by HCDPU prior to purchasing, grading, excavating, clearing, or developing the subject property. HCDPU will not make provisions to extend new water lines to new developments at the county's expense and HCDPU will not provide assistance to upgrade, install or improve the new or existing water services in the proximity of this project unless the developer can provide HCDPU proper justification and demonstrate a benefit for Harnett County. Sewer Public sewer is not available for this development (via Harnett County) Comments: Septic Tanks must be properly sized and installed on each residential building lot to handle the wastewater disposal as HCDPU does not have county sewer available within close proximity of this development. NOTE: The septic tanks for each residential lot must be approved by The Harnett County Environmental Health Department. NOTE: HCDPU provides this information as a curteousy to the developer, registered land surveyor and professional engineer for design purposes. However, HCDPU cannot be held liable for errors, mistakes, ommissions, and inaccurate information provided through this preliminary approval process. It is therefore recommended that the engineer or developer "field verify" the information provided by HCDPU prior to purchasing, grading, excavating, clearing, or developing the subject property. HCDPU will not make provisions to extend new water lines to new developments at the county's expense and HCDPU will not provide assistance to upgrade, install or improve the new or existing water services in the proximity of this project unless the developer can provide HCDPU proper justification and demonstrate a benefit for Harnett County. Page 1 of 2PUBLIC UTILITIES STAFF REPORT