Loading...
HomeMy WebLinkAboutJuly 14, 2025 Work Session MeetingAGENDA Lillington Board of Commissioners Work Session Meeting Lillington Town Hall 102 E. Front Street Lillington, North Carolina 27546 July 14, 2025 8:30am CALL TO ORDER MAYOR GLENN MCFADDEN NEW BUSINESS Item #1 Land Use Plan Briefing Chad Sary, KCI Associates of NC, PA Item #2 Administrative Reports A.Presentation of the Monthly Financial Report Lisa Young, Assistant Town Manager B. Capital Projects Update Alicia Adams, Administrative Services Director C. Presentation of Town Manager’s Report Joseph Jeffries, Town Manager Item #3 Discussion of Regular Meeting Agenda for July 15, 2025 Joseph Jeffries, Town Manager Item #4 Closed Session to Meet per §143-318.11(a)(5) Joseph Jeffries, Town Manager ADJOURNMENT AGENDA ITEM SUMMARY Date of Meeting: July 14, 2025 Staff Work By: Landon Chandler, Planning Director AGENDA ITEM Land Use Plan Briefing ITEM SUMMARY Chady Sary with KCI Associates will go over and discuss the planning for the Land Use Plan. RECOMMENDED ACTION None AGENDA ITEM #1 AGENDA ITEM SUMMARY Date of Meeting: July 14, 2025 Staff Work By: Joseph Jeffries, Town Manager Lisa Young, Assistant Town Manager Alicia L. Adams, Administrative Services Director Ashley Wimberly, Public Works Director Frank Powers, Police Chief John Bethune, Fire Chief William Baker, Parks & Recreation Director Brandon Harris, Assistant Parks & Recreation Director Josh Perry, Planning & Inspections Christy Norris, Youth Programs AGENDA ITEM Administrative Reports. ITEM SUMMARY Monthly reports covering administrative and department activities, financial summaries and public utility usage information RECOMMENDED ACTION Receive information and direct staff, if applicable. AGENDA ITEM #2 CAPITAL PROJECTS UPDATE SCIF Grants Downtown Facilities Stewart, Inc. is continuing to work on the construction drawings for Downtown. Staff has received cost estimates from Duke Energy for relocation of utilities. The Town has entered into a contract with Duke Energy including a non-refundable deposit of $90K. Duke resubmitting their design after adjusting all areas that had conflicts. Staff is continuing to work closely with Ducke Energy and Pike. Staff has provided comments on the construction drawings submitted and those comments are currently being addressed by Stewart. Stewart has submitted final surface stormwater layout to McAdams to incorporate these improvements. McAdams is working through incorporating the final stormwater submitted by Stewart and had this scheduled to be completed by the end of July. Pike Engineering submitted the pedestrian and roadway lighting, but did not include full project6 like requested. Staff has notified them of the error and are awaiting feedback. Pike Engineering is doing both the roadway lighting and the parking lot lighting. Staff has reached out to a Lighting consultant for specialized lighting plans for areas not covered by Duke Energy. Stormwater Resiliency Funds Staff was notified that the State allocated $3.5 million for Stormwater infrastructure improvements and stream restoration, to provide more efficient stormwater management and flood resiliency. Project components will include stormwater management, replacing undersized culverts, and stabilizing streambanks to improve flood resiliency. Projects: 1. Downtown Stormwater Improvements • Construction design is pending site negotiations. • Consultants are coordinating with the railroad RJ Corman to put in an additional crossing. 2. Railroad Crossing • Staff were not successful in partnering with the railroad to complete this project, but the town has infrastructure outside of the railroad piping and we are working to get this repaired. This will improve the flooding that currently happens at this location. There is a large pipe network that belongs to the Town that staff has slated to repair with the flood resiliency funds. Design is underway and CCTV will take place this month. 3. 13th Street Reservoir • McAdams is recommending upsizing the northernmost culvert crossing on S 13th Street to dual RCBC box culverts to eliminate roadway overtopping for the 10 and 25-Year design storms. Although this recommendation is a slight deviation from the 15’W x 6’H RCBC, which is listed as the preferred design alternative (#2) in the previous Town of Lillington Stormwater Assessment, it will better maintain existing stream geometry and lend to more feasible construction and procurement of materials. • Currently staff is working through easement negotiations with the property owners. • Once easements are acquired staff will review final design and the bid package to solicit bidders Golden Leaf Application Stormwater Harnett Street Project Description: The proposed storm drainage improvements would include removal and replacement of existing storm drainage pipe, ranging from 15” RCP to 30” RCP, and removal and replacement of storm drainage structures, including catch basins, drop-inlets, storm drainage manholes, and storm drainage headwalls. The proposed storm drainage infrastructure will effectively capture storm runoff, convey stormwater efficiently inside public right-of-way, and increase the level of service of the storm drainage system. In addition, private storm drainage infrastructure would be relocated to the Town Right-of-Way to allow for easier access for future maintenance and inspections. The probable cost of this project is $1.3 million, the Town has agreed to contribute $250,000 to the project. The Golden Leaf Grant Agreement was approved in June. A project ordinance confirming the Town’s financial contribution was approved at the August Regular Meeting. Staff is working closely with McAdams to get the project moving forward. Construction Drawings are in the final review stages and surface stormwater is being incorporated into the design. Following approval of the construction drawings the project will be solicited for bid. Fire Station #3 Construction has begun on Fire Station #3 located on Hwy 210. The building pad subgrade is set and compaction testing passed. The temporary power pole has been installed. The water line and storm drain will be installed the week of July 14th. The Groundbreaking ceremony will take place Wednesday July 16th at 9am. ARPA S.L. 2022-74 Appropriated Projects All documentation was submitted to the State to fund the Hwy 210 sewer line expansion and Southern Regional Sanitary Sewer/Poorhouse Creek installation of new sanitary sewer interceptor and regional pump station. The total allocation was $9,250,000. Staff has received the offer and acceptance letter from the Department of Water Infrastructure. a. Hwy 210 Sewer line Project Staff is working to close out the project with DWI and should be completed by the end of July. Final payment has already been requested. b. Poorhouse Creek The contractor is continuing to install the sewer force main behind Armtec and the boring contractor is on site for the crossing at Hwy 210 and 401. Following the completion of the boring the contractor will begin to install gravity sewer adjacent to Tractor Supply. The Pump Station site has been cleared. Pump Station work is expected to begin in August. DWI inspected the project and laydown yard during the last progress meeting. LASII Grant Staff submitted the LASII grant application October 2, 2023 requesting $500,000 to develop and implement a new stormwater utility to provide a predictable, equitable and ongoing funding source for its stormwater program. The activities that the Town seeks to accomplish with the funding that the utility will provide include: • Increasing the flood resiliency of the transportation system in and through the Town; • Funding stormwater Capital Improvement Projects (CIPs) to address stormwater quantity and quality issues; • Handling critical maintenance needs and operations; and • Meeting planning and implementation needs. The scoping document was approved by DWI, the grant agreement and the acceptance of funding resolution was approved at the August meeting. The McAdams engineering services contract was approved at the August meeting. The project schedule is two years, with a completion date of August 2026. Staff is continuing to have monthly progress meetings with McAdams. McAdams will spend the next several weeks in Town collecting data on current Stormwater infrastructure. Staff is working to compile the data request submitted by McAdams. S.L. 2023 Appropriated Funds The Town was appropriated $11,062,500 through Session Law in 2023. Administrative cost for the funds is $331,875.00. Available funds remaining are $10,730,625. Additional Proposed projects with remaining funds: 1. Water Tank $4.5 million • Request for Qualifications were accepted at Town Hall July 16th at 2:00pm • Four firms submitted and are currently under review • Request for funding have been approved by DWI and all required documents are on the consent agenda for approval. • Project Ordinance has been approved • Contract with firm was approved and staff will begin working with them in the coming weeks and should have a project schedule timeline. • Weston & Sampson is the selected firm and we are working to locate and acquire a site 2. WWTP project $3.1 million • Request for funding have been approved by DWI and all required documents are on the consent agenda for approval. • Project Ordinance has been approved • Staff is currently working with HRW to complete disbursement request for the project. North Harnett WWTP Capacity Upgrade Harnett County has begun the process of submitting reimbursement requests to the Town for the Town’s portion of the WWTP. Currently, there are two outstanding invoices that Town staff is waiting for DWI to approve. Budget Expended Available 48-00-410-1000 $625,000.00 $277,957.36 $347,042.64 48-00-410-0500 $2,875,000.00 $466,267.82 $2,408,732.18 $3,500,000.00 $744,225.18 $2,755,774.82 Remaining Complete 79%21% Budget Expended Available 75-00-400-2000 $750,000.00 $475,052.78 $274,947.22 75-00-400-2001 $4,750,000.00 $151,326.03 $4,598,673.97 $5,500,000.00 $626,378.81 $4,873,621.19 Remaining Complete 89%11% Budget Expended Available 75-00-400-3000 $375,000.00 $219,464.61 $155,535.39 75-00-400-3001 $2,166,564.66 $2,144,453.23 $22,111.43 75-00-400-3002 $1,185,543.01 $1,170,236.71 $15,306.30 $3,727,107.67 $3,534,154.55 $192,953.12 Remaining Complete 5%95% Budget Expended Available 49-00-410-1000 $200,000.00 $49,021.00 $150,979.00 49-00-410-0500 $1,100,000.00 $0.00 $1,100,000.00 $1,300,000.00 $49,021.00 $1,250,979.00 Remaining Complete 96%4% Capital Projects Construction Hwy 210 Line & Pump Station SRP-W-ARP-0326 PreCon/Engineering Pump Station Line Construction Golden Leaf Harnett Street Storm Drainage PreCon/Engineering Flood Resiliency Projects 2022-2023 PreCon/Engineering Construction SRSS - Poorhouse Creek SRP-W-ARP-0326 PreCon/Engineering Construction Budget Expended Available 75-00-400-4000 $3,150,000.00 $1,977,565.91 $1,172,434.09 $3,150,000.00 $1,977,565.91 $1,172,434.09 Remaining Complete 37%63% Budget Expended Available 50-00-410-0500 $500,000.00 $161,266.17 $338,733.83 $500,000.00 $161,266.17 $338,733.83 Remaining Complete 68%32% Budget Expended Available 41-00-530-1000 $4,832,165.00 $688,776.42 $4,143,388.58 $4,832,165.00 $688,776.42 $4,143,388.58 Remaining Complete 86%14% Budget Expended Available 51-00-400-1000 $3,037,556.00 $0.00 $3,037,556.00 51-00-400-2000 $900,000.00 $0.00 $900,000.00 51-00-400-2050 $3,600,000.00 $0.00 $3,600,000.00 51-00-400-3000 $3,059,006.50 $0.00 $3,059,006.50 $10,596,562.50 $0.00 $10,596,562.50 Remaining Complete 100%0% Budget Expended Available 76-00-400-0500 $220,000.00 $184,137.00 $35,863.00 76-00-400-1000 $55,000.00 $0.00 $55,000.00 $275,000.00 $184,137.00 $90,863.00 SRSS Con Water Tank Pre Con/Eng SCIF Downtown Engineering Construction Fire Station #3 Planning and Design SL 2023-134 Appropriations Act Directed Projects WWTP - Const/Eng Water Tank - Con North Harnett WWTP Capacity Upgrade PreCon/Engineering Golden Leaf Harnett Street Storm Drainage Professional Services Remaining Complete 33%67% AGENDA ITEM SUMMARY Date of Meeting: July 14, 2025 Staff Work By: Joseph Jeffries, Town Manager Lisa Young, Assistant Town Manager Lindsey B. Lucas, Town Clerk AGENDA ITEM Discussion of Regular Meeting Agenda ITEM SUMMARY The purpose of this agenda item is to allow the Town Board an opportunity to ask questions regarding the Regular Meeting agenda for July 15, 2025. RECOMMENDED ACTION No Action Required. AGENDA ITEM #3 AGENDA ITEM SUMMARY Date of Meeting: July 14, 2025 Staff Work By: Joseph Jeffries, Town Manager AGENDA ITEM CLOSED SESSION ITEM SUMMARY The purpose of the closed session per NCGS §143-318.11(a)(5) § 143-318.11. Closed sessions. (a)Permitted Purposes. - It is the policy of this State that closed sessions shall be held onlywhen required to permit a public body to act in the public interest as permitted in this section. A public body may hold a closed session and exclude the public only when aclosed session is required: (5)To establish, or to instruct the public body's staff or negotiating agents concerning the position to be taken by or on behalf of the public body in negotiating (i) the price and other material terms of a contract or proposed contract for the acquisition of real property by purchase, option, exchange, or lease; or (ii) the amount of compensation and other material terms of an employment contract or proposed employment contract. RECOMMENDED ACTION Approve motion to move into closed session discussion. AGENDA ITEM #4