HomeMy WebLinkAboutFinal ACC The Academy Phase 7 Sect 2 Decision PacketFinal ACC The Academy Phase 7 Sect 2 Decision Packet
2/6/2018
1
FINAL DRB DECISION PACKET
Harnett County, North Carolina
Planning Department
108 E. Front Street, Lillington, NC 27546
Phone: (910) 893-7525 Fax: (910) 893-2793
Development Name: ACC THE ACADEMY PHASE 7 SECT 2
Development Type: MAJOR SUBDIVISION PRELIMINARY
PLAN/PLAT
Date: MARCH 23, 2016
The above referenced application
is CONDITIONALLY APPROVED as listed below.
SHORT TERM CONDITIONS, COMMENTS, OR JUSTIFICATIONS
The following conditions are to be rectified prior to obtaining DRB signature and are subject to change during the course of the meeting.
Engineering (910)893-7555 Amanda Bader,abader@harnett.org
Approve:
Fire Marshal (910)893-7580: Bill Lamm blamm@harnett.org
Approve:
GIS/E-911 Addressing (910)893-7523:
GIS@harnett.org Conditionally Approve:
All of the street names were not pre-approved.
Honors Cir is denied. Campus Ct is pending.
Discuss including the beginning of Scholar Dr.
For mapping/E-911 purposes, we need a
recorded access or R/W to properly map this
area and provide accurate data for E-911
Rd Sign Fees $1350.00 due prior to or with DRB
Final submittal.
Planning Department (910)893-7525: Jay Sikes, Landon
Chandler jsikes@harnett.org,lchandler@harnett.org Conditionally Approve:
Please include additional fee of $20 per lot
review - $860 total
Change Landuse to Medium Density Residential
per new Landuse Plan
Note who will maintain drainage easements
Insert setback table on sheet 1
Public Utilities (910)893-7575: Shane Cummings
scummings@harnett.org Conditionally Approve:
A Hydraulic Analysis should be submitted to
demonstrate minimum fire flow and domestic
flow/pressure is available for the future water
main extension.
Downstream sewer analysis should be
submitted.
$250 Preliminary Plan Review Fee is due prior to
Plat Approval.
The combination easement between lots 1159
and 1160 must be 30ft in width.
Final ACC The Academy Phase 7 Sect 2 Decision Packet
2/6/2018
2
The downstream sewer improvements must be
complete.
Note the current phases under construction and utilities
extensions associated with each phase. These utilities
must be installed and approved by NCDENR and HCDPU
prior to approval of this Phase.
Environmental Health (910)893-7547: Bryan McSwain,
Oliver Tolksdorf,bmcswain@harnett.org,otolksdorf@harnett.org Approve:
LONG RANGE CONDITIONS
The following conditions must be satisfied
Must meet all requirements set forth by NC DENR. Contact at (910)433-3300.
Public Utilities (910)893-7575:
Please visit www.harnett.org/utilities for more information on
the approval process.
Capacity fees must be paid in accordance with the latest Water
and Sewer Use Ordinance prior to HCDPU execution of water
and sewer applications.
The EOR must submit to HCDPU Engineered Plans, hydraulic
analysis, and associated documents for review and approval.
The water and sewer utilities must be installed in accordance
with HCDPU standards and specifications.
The EOR must submit all Engineering Final Documents prior to
HCDPU approval of the water and sewer extensions.
The proposed water lines that will serve the proposed phase of
ACC subdivision must be permitted with NCDENR, installed,
inspected, tested and approved by Harnett County Department
of Public Utilities (HCDPU) and NCDENR before the developer
can record the final plat.
The final plat and the As-Built Record Drawings must match
each other. The As-Built Record Drawings and PE
certifications must be submitted to HCDPU for review before
the final plat can be recorded.
The Developer must provide HCDPU a Cost Statement
indicating the cost to install the water lines (materials and
labor) that will serve the lots in this subdivision.
The developer and the utility contractor must provide HCDPU with a one
(1) year warranty on the water and sanitary sewer system
improvements installed to serve the lots in the proposed subdivision.
A FINAL copy, consisting of any corrections, etc., will be sent after the meeting.
Upon resubmittal, additional comments/ corrections may be required.
**Please remember all applicable fee’s**
If APPROVED, your signed plat/plan may be picked up at the Planning Department or will be mailed to you within two (2)
business days. If APPROVED WITH CONDITIONS, you must submit 5 copies of the plat/plan to the Planning Department showing that
all items listed under Short Term Conditions have been rectified. Please be aware that review will not be done while you wait, as all DRB members will have to review the plat/plan for compliance.
If HELD, you must submit 5 copies of the plat/plan showing that all items listed under Short Term Conditions have been
rectified. To attend the next DRB meeting, revised plat/plans must be submitted by noon on Wednesday following the meeting the application was put on hold.
Final ACC The Academy Phase 7 Sect 2 Decision Packet
2/6/2018
3
If DENIED, you may appeal the Board’s Decision to the Harnett County Planning Board within 30 days or meet with
Planning Staff to discuss other potential options.