HomeMy WebLinkAboutpg 6Fog iR
5' MAX.
WIRE SCREEN
WRAPPED AROUND
SANDBAGS BEYOND TO N0.57 STONE
DIVERT WATER TO BOX
ON SLOPES
SECTION "A-An
"MODIFIED" CATCH BASIN INLET PROTECTION
SHEET NO. DWG. NO. EC .6 I OWG. BY PWC
1 OF 1 DATE JAN. 01, 2005 APPROVED BY J.E.G.
NOTES:
1- INLET PROTECTION SHALL BE INSTALLED
IN LOCATIONS AS INDICATED ON THE PLAN.
2. CONTRACTOR SHALL PERIODICALLY AND AFTER EACH
RAINFALL EVENT REMOVE SEDIMENT AND OTHER
DEBRIS FROM AROUND BASIN.
3. SANDBAGS SHALL BE INSTALLED ADJACENT TO
INLETS ON SLOPES, SANDBAGS SHALL NOT
BE INSTALLED ADJACENT TO BASINS IN LOW
AREAS.
PUBLIC WORKS COMMISSION
FAYETTEVILLE, N.C.
WATER RESOURCES
ENGINEERING DEPARTMENT
DATE I REVISION
Slope Installation
- Approximately 200 Staples per Roll (8' or 4'
- AGGREGATE SIZE -USE 2 -3 INCH WASHED STONE
1. Place structural stone (Class B) be the lines and dimensions shown on the plan on a filterfabdc foundation.
InstivetiOns EXCEL I I'"
width) Required - Drawings Not to Scale V Figure E
Amigo
2. Keep the center shine section at least 9 inches below the end where the dam abuts the channel banks.
L= THE DISTANCE SUCH
THAT A & B ARE OF
Widefilanket Shown
EQUAL ELEVATION
WEIR
4. Provide an apron that is 3 what; the height of the dam. The apron width's at least 4 feet long. Underout
A L B f- HEIGHT
Figure C
-
5. Extend the stone at least 1.5 feet beyond the ditch bank to keep water from cutting wound the ends of the
check dam.
Step 1 -Site Preparation
" ea,•aa ''�
'
Coronado
x x x
Prepare site to design profile and grade. Remove
;y"s
1
+-e
�MINI'��
debris, rocks, clods, etc.. Ground surface should
•;_ins -
--�
x x x
be smooth prior to installation to ensure blanked
needed.
Houndog
VEHICULAR ACCESS, STABILIZE
remains in contact with slope.
�� >..• :-;: Figure F
Anticipate submergence and deposPoon above the check dam and erosion from high goys around the edges of
SLOPES WITH MATERIAL SUITABLE
Step 2- Seeding
Crotmd . +z "-` r _° :
Olympic
Yam
x x x x
Seeding of site should be conducted to design
Surface, v-q-``
;„ s: r :'•
be taken such as, installing a protective npmp liner in that portion of the channel
_
requirements or to follow local or state seeding
y`';
^Q =a,' Fi
Remove sediment accumulated behind the dams as needed to prevent damage to channel vegetation, allow the
z x
requirements as necessary.
`, ,",..: =',t•
FFigur'eE
gure
channel to drain thmugh the stone check dam, and prevent large flows from carrying sediment over the dam.
A
soil may require longer staples.
Ste 3 - Staple Selection
'
IIFI
At a minimums, 6" long by 1" crown, D gauge staples
-`F' ,
c Ground
BASIN CONSTRUCTED
are to be used to secure the blanket to the ground
} .., '-' -' -'
- ENTIRELY IN CUT,
Figure D - Plan View
surface. hstallazion in roc , sand m other loose
ky y
Figure
soil may require longer staples.
slopes and the upstream terminal end of the channel
JII -I II
II I II II- I I
BASIN CAPACITY AND SOILS
to serum the edges of the blanket. The trench should
Step 4 - Excavate Anchor Trench and Secure
~�`: _i. _ r� M :•`�' +'^
10
- --
Blanket
DISCHARGE
Excavae a trench along the top of the slope to secure
Figure E
Figure A
x -omaa swtrt«.1m
the upstream and of the blanket. The trench should
AND GRADE VARIES I II -I -
I 3:1
(DITCH) ®GRADE
rush along the length of the installation, be 6' wide
and 6' deep. Staple blanket along bottom of trench,
fill with compacted soil overlap blanket towards toe
in
Mmkda !
-_
INTO POND (NO APRON)
of slope and secure with row of staples (shown
Figures A, E and F)
slawiwa
nt =roam r eraok «z
?
_
Figure E -
Plan View -nom sant"tmam
Step 5 - Secure Body of Blanket
v
le
Roll blanket down slope rom anchortrench S le
Pe Slop
Figure B - Profile View Figure C - Cross Section View
crovnd set
blanket underneath upstream blanket to from shingle
of blanket following the pattern shown in Figure
crowd litre
pattern Staple seam as shown in Figure E. Seems
tits
D. Leave end of blanket ansta led to allow for
D P
Excel R -1 is produced by Western Excelsior and consists of a temporary Rolled Erosion Control
1 ;t
❑minimum staples to be used. More staple, maybe
over) shown in Figure B. Place downstream
'p
Figure B - Profile View
Figure C -Cross Section View
pholadegradable synthetic net (top). The expected longevity of Excel R 1 is approximately 12
u
blanket underneath upstream blanket to from shingle
resist mowers and foot traffic and to am= blanket is
months (actual longevity dependent on field and climatic conditions). Excel R -1 is manufactured
Product Application/Equivalency $purifications
parent. Staple seam as shown in Figure E. Secure
downstream blanket with stapling pattern shown N
, W
Figure a Stapling pattern shown in Figure D reflects
Excel R -1 is produced by Western Excelsior and consists of a temporary Rolled Erosion Control
innnum staples to be used. More staples be
m P P may
e
Product (RECP) comprised of an excelsior matrix mechanically (stitch) bound m a single,
Figure E
required to amine blanket is sufficiently seared to
Ph otode adable synthetic net m The expected longevity of Excel R -1 is approximately 12
gr Yn (top). xP g ty PPro Y
1 `
resist mowers and foot traffic and m ensure blanket is
months (actual longevity, dependent on field and climatic conditions). Excel R -I is manufactured
in contact with soil surface war the emhe area of
to include physical properties sufficient m provide the intended longevity and performance.
P Y P l>e pr g lY Pert
Figure F - Profile View
blanket. Further, critical points rary¢e additional
staples. Critical points are identified in Figure G.
Product specifications may be found on document WE EXCEL-RI-SPEC and performance
cmi Fors
edge- e-
terminal edge.
information may be found on document WE_EXCEL_Rl_PERF. All documents are available
Step 6 - Continue Along Slope- Complete
from Western Excelsior Technical Support or www.westemescelsior.com. Additional to above,
cdumt ro ,
Installation
equivalent products to Excel R -1 must meet identical criteria as Excel II as follows:
Figure G - Critical Points
Overlap adjacent blankets as shown in Figure C and
I
T__ ..
repeat Step 5. Seems toe of slope using stapling
1. Consist of machine produced, weed and debris free excelsior bound to a angle, synthetic,
rmwai em
pattern shown in Figure E. Secure edges of
photadegmdable net
count Sa&ce
installation by stapling at 101 intervals along the
2. Sufficient tensile strength, thickness and coverage to maintain integrity ty durin installation
s,ara
terminal edge.
and ensure material performance.
3. Listing within AASHTO NTPEP database.
Document a WE EXCEL RI SO
4. Meet ECTC specification for category 2C products.
Figure G - Critical Point Securing
12" OF NCDOT NC
OR NO 57 STONE
CLASS B RIP RAP
APRON LENGTH =
DAM HEIGHTx3, 4'
1.5' MIN.
I
LU
ax 1-
�� w
U
7
SECTION A -A
FILTER
FABRIC
12" OF NCOOT NC
OR NO 57 STONE
CLASS B RIP RAP
APRON LENGTH =
DAM HEIGHTx3, 4'
1.5' MIN.
W
g�F
U
7
FILTER
SECTION A -A FABRIC
ROCK CHECK DAM DETAIL
NTS
PERMANENT SEEDING SPECIFICATION
1. All disturbed areas shall be dressed to typical sections and plowed to a depth of 5 inches.
The top 2 Inches shall be pulverized to provide uniform seedbed. NOTE: Line should be applied
with necessary equipment to give uniform distribution of these materials. The hand - bucket
method is not acceptable. Lime and fertilizer should be incorporated Into the soil prior to
2 The following are rates and kinds of these materials to be applied PER ACRE:
M RATES.
Abruzzi Rye 5D lbs.
Pensacola Bohiogross 50 lbs.
Kentucky 31 Fescue 50 lbs.
Korean Lespedezo 15 lbs.
Common Bermudagross 25 Ibe.
10 -20-20 Fertilizer 500 lbs.
Agricultural Limestone 4000 lbs.
CONSTRUCTION SPECIFICATIONS
- AGGREGATE SIZE -USE 2 -3 INCH WASHED STONE
1. Place structural stone (Class B) be the lines and dimensions shown on the plan on a filterfabdc foundation.
Anthem Adventure
The crest wkah of the dam should be a minimum of 2 feet
Amigo
2. Keep the center shine section at least 9 inches below the end where the dam abuts the channel banks.
L= THE DISTANCE SUCH
THAT A & B ARE OF
3. Place sediment control stone (#5 or 957) on the upstream of the dam that is minimum of 1 foot thick
EQUAL ELEVATION
WEIR
4. Provide an apron that is 3 what; the height of the dam. The apron width's at least 4 feet long. Underout
A L B f- HEIGHT
the apron so that the top of the apron is flush with the surrounding aside.
-
5. Extend the stone at least 1.5 feet beyond the ditch bank to keep water from cutting wound the ends of the
check dam.
Crossfire II Chesapeake
6. Excavate sediment storage area to the dimensions shown an the plan.
Coronado
MAINTENANCE
pp
inch
e at
Inspect dams and channel weekly and each
1
+-e
�MINI'��
Genesis Finelawn Petite
limbs, or could clog channel when
other debits that c
and repair immediately. Clean out sediment, stow, Ilmbs, or Omer debits mat eoukl ebg Nechannel
d repair im sediment,
--�
MAY VARY TO PROVIDE
Jaguar Grande
needed.
Houndog
VEHICULAR ACCESS, STABILIZE
MIN
Kentucky 31
Anticipate submergence and deposPoon above the check dam and erosion from high goys around the edges of
SLOPES WITH MATERIAL SUITABLE
Pacer Montauk
Mustang
9
Olympic
Yam
the dam. Cored all damage immediately. If significant emsion occurs between dam. additional measures can
Rebel Phoenix
Rebel Jr.
FILTER
be taken such as, installing a protective npmp liner in that portion of the channel
_
Safari
FABRIC
Remove sediment accumulated behind the dams as needed to prevent damage to channel vegetation, allow the
Figure D - Plan View
Tomahawk Shenandoah
Wolfpack Trailblazer
Tempo
Tribute
channel to drain thmugh the stone check dam, and prevent large flows from carrying sediment over the dam.
A
soil may require longer staples.
Add stones to dams as needed to maintain design height and cross section.
12" OF NCOOT NC
OR NO 57 STONE
CLASS B RIP RAP
APRON LENGTH =
DAM HEIGHTx3, 4'
1.5' MIN.
W
g�F
U
7
FILTER
SECTION A -A FABRIC
ROCK CHECK DAM DETAIL
NTS
PERMANENT SEEDING SPECIFICATION
1. All disturbed areas shall be dressed to typical sections and plowed to a depth of 5 inches.
The top 2 Inches shall be pulverized to provide uniform seedbed. NOTE: Line should be applied
with necessary equipment to give uniform distribution of these materials. The hand - bucket
method is not acceptable. Lime and fertilizer should be incorporated Into the soil prior to
2 The following are rates and kinds of these materials to be applied PER ACRE:
M RATES.
Abruzzi Rye 5D lbs.
Pensacola Bohiogross 50 lbs.
Kentucky 31 Fescue 50 lbs.
Korean Lespedezo 15 lbs.
Common Bermudagross 25 Ibe.
10 -20-20 Fertilizer 500 lbs.
Agricultural Limestone 4000 lbs.
CONSTRUCTION SPECIFICATIONS
1. Place structural stone (Class B) to the lines and dimensions shown on the plan on a fitter fabric foundation.
The meat wklth of the dam should be a minimum of 2 feet.
2. Keep the center stone section at least 9 inches below the end where the dam abuts the channel banks.
3. piano sediment central stone (#5 or 057) on the upstream of the dam that is minimum of 1 foot thicit.
4. Povkte an apron that is 3 times the height of the dam. The apron width is at least 4 feet long. Undemut
the apron so that the top of the apron is flush with the surrounding grade.
5. Extend the stone at least 1.5 feet beyond the d0ch bank to keep water from cutting around the ends of the
check dam.
6. Excavate sediment storage area to the dimensions shown an the plan.
MAINTENANCE
Inspect check dams and channels at least weekly and after each significant (12 inch or greater) rainfall event
and repair immediately. Clean out sediment, straw, limbs, or other debris that could clog the channel when
needed.
Anticipate +submergence and deposition above the check dam and eosion from high fkr s around the edges of
the dam. Conect all damage immediately. If significant emsion occurs between dams, additional measures can
betaken se. ch as, installing a protective Ingrain liner in that portion of the channel
Remove smliment accumulated behind the dams as needed to prevent damage to channel vegetation, allow the
channel to drain through the stone check dam, and prevent large flows from carrying sediment over the dam.
Add stones to dams as needed to maintain design height and woss section.
ROCK CHECK DAM WITH WEIR DETAIL
N I'i
RIPRAP ALL SLOPE'(IF ANY) TOE OF'OUTLET APRON \
FROM PIPE END TO PROTECTION FLUSH SOILS SUITABLE
BOTTOM RIPRAP APRON
WITH BASIN BOTTOM FOR INFILTRATION
(PROVIDE DETAILED
ON SITE SOILS REPORT)
COMPACTED OIL MIN.`•` .
SOIL
3' ,��
`r^�4
>�..i�tJ�: "yn�i•^,`s 18" MIN.
' �6' TYPICAL --1.
TEMPORARY EARTHEN DIVERSION BERM
COARSE
1- W TYPICAL
TEMPORARY GRAVEL DIVERSION BERM
INFILTRATION BASIN DETAIL
NTS
3:
41 )Ti IL ` Channel Installation
Approved Tall Fescue Cultivars:
- AGGREGATE SIZE -USE 2 -3 INCH WASHED STONE
Instructions EXCEL R -I "
Anthem Adventure
Adventure II
Amigo
wide Blanket Shown
Figure F Figure B/
Austin Apache
Apache II
Arid
3. Ensure that the top of the dike is not lower at any point than the
Chapel Hill Brookstone
Bonanza
Bonanza 11
Prepare site m design profile and grade. Remove
Crossfire II Chesapeake
Chieftain
Coronado
1;0
�
Falcon Debutante
Duster
Falcon
SLOPE ABOVE POND HWL
Genesis Finelawn Petite
Finelawn
Finelawn I
MAY VARY TO PROVIDE
Jaguar Grande
Guardian
Houndog
VEHICULAR ACCESS, STABILIZE
Monarch Jaguar 111
Kentucky 31
Kitty Hawk
SLOPES WITH MATERIAL SUITABLE
Pacer Montauk
Mustang
9
Olympic
Yam
FOR SLOPE GRADE
Rebel Phoenix
Rebel Jr.
Pixie
Pyramid
K
_ �' Figure '•' ° �: �' _ _ _ - "�"
Safari
Rebel II
Renegade
Figure D - Plan View
Tomahawk Shenandoah
Wolfpack Trailblazer
Tempo
Tribute
Titan
Vegas
II
soil may require longer staples.
IIFI
Wrangler
Step 4 - Excavate Anchor Trench and Secure
c Ground
BASIN CONSTRUCTED
Fy y 1
- ENTIRELY IN CUT,
- '•,••1: >° -" Surface
_ NO FILL AREA
`
slopes and the upstream terminal end of the channel
JII -I II
II I II II- I I
BASIN CAPACITY AND SOILS
to serum the edges of the blanket. The trench should
I
CAPABLE OF RETAINING
10
- --
- STORM WITH NO
DISCHARGE
-
PIPE INLET. SIZE - -
L .
_ -_YEAR
towards too of slope and secure with row ofsrsples
AND GRADE VARIES I II -I -
I 3:1
(DITCH) ®GRADE
(shown in Figures A,E and 4
Mmkda !
-_
INTO POND (NO APRON)
"N
r-oenr an-rrnu a n rrr raru WAY
9
CONSTRUCTION SPECIFICATIONS
1. Place structural stone (Class B) to the lines and dimensions shown on the plan on a fitter fabric foundation.
The meat wklth of the dam should be a minimum of 2 feet.
2. Keep the center stone section at least 9 inches below the end where the dam abuts the channel banks.
3. piano sediment central stone (#5 or 057) on the upstream of the dam that is minimum of 1 foot thicit.
4. Povkte an apron that is 3 times the height of the dam. The apron width is at least 4 feet long. Undemut
the apron so that the top of the apron is flush with the surrounding grade.
5. Extend the stone at least 1.5 feet beyond the d0ch bank to keep water from cutting around the ends of the
check dam.
6. Excavate sediment storage area to the dimensions shown an the plan.
MAINTENANCE
Inspect check dams and channels at least weekly and after each significant (12 inch or greater) rainfall event
and repair immediately. Clean out sediment, straw, limbs, or other debris that could clog the channel when
needed.
Anticipate +submergence and deposition above the check dam and eosion from high fkr s around the edges of
the dam. Conect all damage immediately. If significant emsion occurs between dams, additional measures can
betaken se. ch as, installing a protective Ingrain liner in that portion of the channel
Remove smliment accumulated behind the dams as needed to prevent damage to channel vegetation, allow the
channel to drain through the stone check dam, and prevent large flows from carrying sediment over the dam.
Add stones to dams as needed to maintain design height and woss section.
ROCK CHECK DAM WITH WEIR DETAIL
N I'i
RIPRAP ALL SLOPE'(IF ANY) TOE OF'OUTLET APRON \
FROM PIPE END TO PROTECTION FLUSH SOILS SUITABLE
BOTTOM RIPRAP APRON
WITH BASIN BOTTOM FOR INFILTRATION
(PROVIDE DETAILED
ON SITE SOILS REPORT)
COMPACTED OIL MIN.`•` .
SOIL
3' ,��
`r^�4
>�..i�tJ�: "yn�i•^,`s 18" MIN.
' �6' TYPICAL --1.
TEMPORARY EARTHEN DIVERSION BERM
COARSE
1- W TYPICAL
TEMPORARY GRAVEL DIVERSION BERM
INFILTRATION BASIN DETAIL
NTS
3:
41 )Ti IL ` Channel Installation
"Approximately 300 Staples per Roll (8' or 4f
Required Drawings Not to Sole W
- AGGREGATE SIZE -USE 2 -3 INCH WASHED STONE
Instructions EXCEL R -I "
width) -
objectionable material.
�-v
wide Blanket Shown
Figure F Figure B/
WIDTH - 12 FT. MINIMUM OR FULL WIDTH AT ACCESS
V
Figure E
3. Ensure that the top of the dike is not lower at any point than the
Step 1 - Site Preparation
Figure C
LOCATION - LOCATE CONSTRUCTION ENTRANCES AND
Prepare site m design profile and grade. Remove
Figure C
and clea scut
debris, tucks, clads, etc.. Limited surface should
1;0
�
CONSTRUCTION VEHICLES. AVOID STEEP GRADES
be smooth prior to installation to ensure blanket
+ ' rocket +
in place less than 30 working days.
remains in contact with slope.
_
z z x I x
Step 2 - Seeding
:.y:'(�'.: + auM, «z _ _t:•: e j ;.
z " x x x
Seeding of site should be conducted to design
remove sediment from the flow wets and repair the diverao, ridge. Carefully
-
CONTRACTOR SHALL SUPPLEMENT AND MAINTAIN GRAVEL
requirements arm follow local wastes seeding
.
natural ground level and appropriately stabilize it.
requirements as necessary.
' i : _ _ _ _ ,:v.r •' `. r
•
x x
Step 3 - Staple Selection
'- , ^ _
At a minimum, 6" long by 1" cows, I I gauge staples
_ �' Figure '•' ° �: �' _ _ _ - "�"
x - nmmswgera.am
are in be used to secure the blanket m the ground
°. main «a
Figure D - Plan View
surf ace. lnsWlationinrocky ,sandyarotherloose
_'' *� "�•:'' _
soil may require longer staples.
Step 4 - Excavate Anchor Trench and Secure
c Ground
Fy y 1
Blanket
- '•,••1: >° -" Surface
of the channel side
Excavate a trench along the top nn
slopes and the upstream terminal end of the channel
Figure A
x .nom savt"r�wm
to serum the edges of the blanket. The trench should
run along the length and width office installation, be
6" wide and 6" deep. Staple blanket along bottom of
Saw ExasI
trench, fill with compacted soil, ovedap blanket
A�
towards too of slope and secure with row ofsrsples
¢���)e Bmdecir etn,xaz
W 1A,�I ,
Figure E - -
(shown in Figures A,E and 4
Mmkda !
Plan View
Step 5 - Secure Body of Blanket
"N
Roll blanket down slope from anchortrench. Staple
arom a yam armed a d.I
body of blanket following the pattern shown in Figure
D. Leave end of blanket unstapled to allow for
overlap shown in Figure B. Place downstream
Figure B - Profile View Figure C - Cross Section View
blanket underneath upstream blanket to from shingle
V
Product Application/Equivalency Specifications
pattern Staple seam as shown in Figure E. Seems
tits
downstream blanket with stapling pattern shown in
Figure D. Stapling pattern shown in Figure D mature.
Excel R -1 is produced by Western Excelsior and consists of a temporary Rolled Erosion Control
1 ;t
❑minimum staples to be used. More staple, maybe
Product (RECP) comprised of an excelsior matrix mechanically (stitch) bound to a single,
Figure E
required m ensure blanket is sutHciendy secured to
pholadegradable synthetic net (top). The expected longevity of Excel R 1 is approximately 12
,,
resist mowers and foot traffic and to am= blanket is
months (actual longevity dependent on field and climatic conditions). Excel R -1 is manufactured
in contact with sail surface over the enthe area of
to include physical properties sufficient to provide the intended longevity and performance.
Figure F - Profile View
blanket. Further, critical points require additional
Pmduct specifications rosy be found on document WE EXCEL Rt SPEC and performance
staples. Critical points are identified in Figure G.
information may be found on document WE_ EXCEL PERF. All documents are available
Step 6 - Continue Along Slope - Complete
Installation
_RI
from Western Excelsior Technical Support or www.westemexcelsior.com. Additional to above,
equivalent products to Excel R -1 must meet identical criteria as Excel R-1 as follows:
crew mrsmrs sea mrsoya
Overlap adjacent blankets as shown in Figure C and
i. Consist of machine produced, weed and debris free excelsior bound to a single, synthetic,
repeat Step S. Secure me of slope using stapling
photodegradable set
re mrsmrr
patent shown in stapling E. Serum edges of
fermi al stapling at 1.0' intervals along the
2. Sufficient tensile strength, thickness and coverage to maintain integrity during installation
BntY g
_
edge- e-
terminal edge.
r
and ensure material performance.
3. Listing within AASHTO NTPEP database.
Document#WE EXCEL RI CB
- - -
4. Meet ECTC specification for category 2C product
Figure G - Critical Points
i -
I
T__ ..
I
Fertilizer used for topdressing on all roadway areas except slopes 2:1 and steeper shall be 10 -20-20
written approval of the Engineer, a different analysis of fertilizer may be used provided grade and shall be
applied at the rate of 5DO pounds per acre (561 per hectare). Upon the 1 -2 -2 ratio Is maintained
and the rate of application adjusted to provide the same amount of plant food as 10 -20 -20 analysis.
Fertilizer used for topdressing on slopes 2:1 and steeper and waste and borrow weas shall be 16 -8-8
grade and shall be applied at the rote of 500 pounds pin acre (560 kg par hectare). Upon written
approval of the Engineer, a different analysis of fertilizer may be used provided the 2 -1 -1 ratio Is
maintained and the rote of application adjusted to provide the same amount of plant food as 16 -8 -8
analysis.
March 1 - August 31 September 1 - February 28
51 (551 Tall Fescue 50# (551 Tall Fescue
2•ir# (2Bkg) Bermudogross (hulled) 35# (40kg) Sentrudogross (unhulled)
500# (51 Fertilizer 500$ (560109) Fertilizer
4000# (4500kg) Limestone 4000# (4,'iWkg) Limestone
Slopes 21 and Steeper and Waste and Borrow Lomrtlons:
March 1 - August 31 Septernber 1 - February 28
751 (85kg) Tall Fescue 75/1 (81 Tall Fescue
25# (281ag) Bermudagross (hulled) 35# (40kg) Bermudagraw ( unhulled)
500# (560kg) Fertilizer 500# (5601,9) Fertilizer
4000# (4500kg) Limestone 40001/ (4500kg) Limestone
6' EMERGENCY n.
MIN.1 (IN STABLE SOIL)
TOP OF BANK WhA NN41"Is EMBANKMENT STABILIZED
WITH VEGETATION
NATURAL GRO ND
I
x.
r
•,tw. •r •S.• i• =•
0 GRADE
DESIGN CRITERIA
CONSTRUCTION SPEC- .IFICATONS
- AGGREGATE SIZE -USE 2 -3 INCH WASHED STONE
I. Remove and properly dispose of all trees, brush, stumPe. an other
objectionable material.
DIMENSION OF GRAVEL PAD
THICKNESS - 6 INCHES MINIMUM
2. Ensure that the minimum constructed cross section me.ets all design
WIDTH - 12 FT. MINIMUM OR FULL WIDTH AT ACCESS
requirements.
POINTS OF THE VEHICULAR ENTRANCE AND DOT
3. Ensure that the top of the dike is not lower at any point than the
AREA, WHICHEVER IS GREATER
LENGTH - 50 FT. MINIMUM.
design elevation plus the specified settlement.
LOCATION - LOCATE CONSTRUCTION ENTRANCES AND
4. Provide sufficient room wound diversions to permit machine regrading
EXITS TO LIMIT SEDIMENT FROM LEAVING THE SITE
and clea scut
AND TO PROVIDE FOR MAXIMUM UVUTY BY ALL
1;0
�
CONSTRUCTION VEHICLES. AVOID STEEP GRADES
S. Vegetate the ridge Immediately after construction, unless R will remain
AND ENTRANCES AT CURVES IN PUBLIC ROADS.
in place less than 30 working days.
CONTRACTOR SHALL INSTALL ADDITIONAL GRAVEL
LL
CONSTRUCTION ENTRANCES NOT INDICATED ON THE PLANS
MAINTENANCE
REQUIRED FOR STAGING ANI BORROW AREAS AND
Inspect temporary diversions once a week and after every ndnfoll. Immediately
MAINTAIN AT NO ADDITIONAL EXPENSE TO THE OWNER
remove sediment from the flow wets and repair the diverao, ridge. Carefully
-
CONTRACTOR SHALL SUPPLEMENT AND MAINTAIN GRAVEL
check outlets and make timely repairs as needed. When III,. area protected
is permanently stabilized. remove the ridge and the channel to blend with the
CONSTRUCTION ENTRANCES AT HIS EXPENSE UNTIL FINAL
natural ground level and appropriately stabilize it.
ACCEPTANCE
m
TEMPORARY DIVERSION BERM DETAILS
NTS
THIS WORK SHALL CONSIST OF FURNISHING, PLACING MAINTAINING AND REMOVING A "GUTTERBUDDY' TYPE
SEDIMENT CONTROL DEVICE AS DIRECTED BY THE ENGINEER AND AS
SHOWN ON THE PLANS FOR A TYPICAL 2'1 CATCH BASIN, THE • GUTTERBUDDY' SHOULD BE PROVIDED WITH A
MINIMUM LENGTH OF 8f. EACH END OF THE FILTER SOCK SHOULD BE SECURELY INSTALLED INTO THE BACK OF
THE CATCH BASIN BETWEEN THE HOOD AND THE GRATE A MINIMUM OF 61 OFF EACH END OF THE FILTER
SOCK SHOULD BE SECURED INTO THE CATCH BASIN IN THIS MANNER.
CURB INLET
mm mreuuur
THE FILTER SOCK SHOULD BE INSPECTED AFTER EACH RUNOFF PRODUCING RAINFALL OR AT LEAST ONCE PER
WEEK. IF THE INSPECTION SHOWS SILT AND DEBRIS BUILD UP ON OR AROUND THE FILTER SOCK, THEN THE
FILTER SOCK SHALL BE CLEANED OR REMOVED AND REPLACED IF NECESSARY.
LAST SAVED: 1/28/2013 3:54 PM LAST PLOTTED: 1/28/2013 3:56 PM PLOTTED BY: Ron Wiliam$ FILENAME: G: \CURRENT JOBS \WEAVER FRANK \10 - 1224 -01 THE SUMMIT - SECTION FOUR\ PLANS \DETAILS \MASTER- DLTAILS.DWG
FILTER SOCK 'MODIFIED° INLET PROTECTION
••'VITERBUDDY'•
NTS
CONSTRUCTION SPECIFICATIONS
1. Infiltration basin shall be constructed level (at a 0 -0.05% grade). Do not construct a basin on a slope
greater than 15 percent. Do not locate within fill soils. Do not construct basin in a location with less
than 2 feet between the bottom of the infiltration basin and the seasonal high groundwater table,
underlying Impervious soils, or bedrock (minimum 4 foot separation is recommended). Basin shall not be
constructed if it causes water problems to downgradient properties. It must be a minimum of 15 feet down -
gradient from structures, located a minimum of 100 feet horizontally from any water supply well, 50 feet
from Class SA waters and 30 feet from any surface water.
2. Pretreatment device for removing sediment and solids must be used to protect infiltration devices from
clogging. These pretreatment devices include filter strips, gmssed swales /ditches with check dams, concrete
sumps and forebays (sediment traps).
3. If inlet flow is a concentrated source of discharge, an energy dissipater shall be used.
4. A site- specific hydrogeologic investigation shall be performed to establish the suitability of soils for
the infiltration basin. Suitable soils must have an infiltration rate of 0.52 inches per hour or greater.
5. Sizing of infiltration basin shall meet the specifications set forth in the NCDENR Stormwater BMP Manual
and must be able to completely dewater within 5 days.
6. The bottom of the infiltration basin most be lined with a layer of clean sand with a depth of 4 inches
or greater, unless the native soil is equivalent (II fines or less).
7. Contractor shall use care during construction to minimize compaction of soil on the bottom and walls
of the infiltration basin. light equipment and construction techniques that minimize compaction shag be used.
8. A minimum of one observation well shall be installed to periodically verify that the drainage media
is fully draining. The monitoring well shall consist of a 4 to 6 inch diameter, perforated polyvinyl chloride
(PVC) pipe with a locking cap. The well shall be placed near the center of the facility or in the general
location of the lowest point within the facility, with the invert at the excavated bottom of the facility.
OPERATION AND MAINTENANCE
The drainage am shall be carefully managed to reduce the sediment load to the infiltration bas i
n
Immediately after the infiltration basin is established, the vegetation will be watered twice weekly if
six weeks). No portion of the infiltration basin shall be fertilized after the initial fertilization required to establish
needed until the plants become established (commonly x ) p tration b ha req
"o in around the basin will be maintained at a height of approximately six inches. After the infiltration basin is established it shall be
the vegetation. The vegetation n t and
g g
gh
inspected once a quarter and within 24 hours after every storm event greater than 1.0 inches. Records of operation and maintenance shall be kept in a known set location
and be available upon request
Operation and Maintenance Provisions:
1. Remove any bash/debris if present from the entire BMP.
2. If any areas of bare soil and /or erosive gullies have formed around the perimeter of the infiltration basin, regrade the soil if necessary to remove the gully, then
plant ground cover and provide a one time application of time and fertilizer and water until established.
3. Dispose of any sediment and unclog if applicable any inlet pipe or swale /ditch. If erosion is emoting in the swale /ditch regmde the Swale /ditch if necessary to
smooth it over and provide erosion control devices such as reinforced turf matting or riprap to avoid future problems with erosion.
4. If sediment has accumulated in the forebay, (sediment trap) and reduced the depth to 75% of the original design depth, find the source of the sediment and remedy
the source. Remove the sediment and dispose of where it will not impact any drainage area. If erosion has occurred or riprap is displaced, provide additional erosion
protection such as reinforced turf matting or additional riprap to prevent future erosion. B weeds are present remove by hand if Possible or use a selective herbicide to
prevent killing of preferred ground cover.
5. If a visible layer of sediment has accumulated in the main infiltration area, search for the source and remedy the problem. Remove the sediment and dispose of
c n edits at was removed in the v r areas immediately. If water is standing more
where it will not impact any drainage area. Replace any media that process and re egetate disturbed y g
than 5 days after a storm, event, replace the top few inches of filter media and see if this corrects the problem. If so revegetate immediately, if not consult an appropriate
professional for a more extensive repair. If weeds or noxious plants are growing, remove the plants by hand or wipe with herbicide (do not spray).
6. If the embankment has shrubs or trees sprouting or growing, remove immediately, if the embankment requires repair during an annual inspection by an
appropriate professional, make all needed repairs.
7. B the outlet device has clogged or is damaged, clean and dispose of the sediment properly and repair or replace the outlet device.
w�•ii'•lihiir•i ii•-ii !�•i�•i'i� "i i+�ii•i`ARVIkC.••+.,.• - • I • I �- -�.
N •irr .'i•i�i+•li�i!iti�i! l� 074tj ���•i��•irsfi �i
is
•y..;c.�•r.. ,. .
� �••err.• u •'••••"�
•err
•:t:T•vt. ••:• • • - .•
•i '•ii?}i�:�� •••4i•� ••r�ii•e••�eJ•� •iii i• • •• ti •• •• •
••••q•y••••ri•••�i • ••• • • • • , .
• •<. •j • • e• • • •ti ••
-0 • •' •''M• �i� • • • • r • • r .
•• • • T�•e•• ••••V•••••.•• ••••••
i�i'":•�•ii•••i:•�••i�••, �•.•i �i• se
w as
DRAWN BY: RSW / CCB
CHECKED: JMK, JR.
1 REVIEWED: '
JMK, JR.
DATE:
DECEMBER 2010
W
D
O
Z CJ
J
OJ
1� LL z
UJ
W
r Q
tJJ
W C) a w_
O
Of IL
d �
Cy fY
G LJJ
>
r�r� �
VO
W
w ti
O O
r 3
m 4
J
O
O
U
to
O
D W
or O
O
a
F
Z
W
M
N
1x \11111111 trrryr
max` P � '••�^ ��%
Q
QU
I-
Z
O''izOi�••
... J>
1;0
�
rrrr 11 tit\ \ \`v1
Z
NCw
t®
N
w
0
!V
IL 4B Yi
SCALE HOR. 1"-40'
VERT. 1 "4
BOOK NO.
6916
SHEET
6 OF 14
II
O
W
M
N
QU
I-
Z
�
o
0Ji`�O
LL
J
M
in
U-
<
>
LO
ao
mW
tt
m
t
C:)
Z
I•:7
O
(�
Lll
�LLaaJ
Z
NCw
t®
N
w
0
!V
IL 4B Yi
SCALE HOR. 1"-40'
VERT. 1 "4
BOOK NO.
6916
SHEET
6 OF 14