PUBLIC UTILITIES STAFF REPORT
Harnett County, North Carolina
Planning Department
108 E. Front Street, Lillington, NC 27546
Phone: (910) 893-7525 Fax: (910) 893-2793
Development Name: Patton Point Phases 2 & 3 – Preliminary
Property Description
PIN(s): 9597-21-7877.000 & 9597-40- Acreage: 65.90 acres
8981.000
Address/SR No.: Tingen Road (SR 1139) and Micro Tower Road (SR 1140)
Water
Public water is available for this development (via Harnett County)
Water capacity is available for this development
Nearest water line location (Road name & SR#): Tingen Road (SR 1139)
Nearest water line size: 6”
Fire flow is available for this development
Lines permitted under DENR Permit: (DEH Serial Number)
Sewer
Public sewer is not available for this development (via Harnett County)
Sewer capacity is not available for this development
Nearest sewer line location (Road name & SR#):
Lines permitted under DENR Permit: (DWQ Serial Number)
Additional Requirements
As-Built Record Drawings Yes No N/A
Cost Statement for water improvements Yes No N/A
Cost Statement for sewer improvements Yes No N/A
Professional Engineer’s Certifications for water/sewer extension Yes No
N/A
Final Plat & As-Built Record Drawings are identical Yes No N/A
DOT Encroachment Agreement Yes No N/A
Distance to nearest water/sewer lines noted (Site Plan Only) Yes No N/A
Master Plan submitted for additional phases if intended Yes No N/A
Ballot
REVIEWER: Tim Payseur Date: Jan 15, 2008
VOTE: Conditionally Approve
CONDITIONS:
SHORT TERM:
The Developer must provide HCDPU with a Master Development Plan for the entire
development.
The water and sewer lines for this development must be permitted by NCDENR and approved
by HCDPU.
The Developer must enter into a three party NCDOT Encroachment Agreement with HCDPU and
NCDOT.
The note on Page 2 of the Preliminary Plat should indicate the future water line to be installed
by the developer not by others. A 6” water line must be extended along Tingen Road (SR
1139) to serve Phase 3 of this development.
Page 1 of 2 PUBLIC UTILITIES STAFF REPORT
LONG RANGE:
Please visit www.harnett.org/utilities for more information on the approval process.
The developer must provide utility plans, and engineers report, project specifications along with
the NCDENR applications to HCDPU for review and approval. No construction may begin on the
water lines without the required NCDENR permits.
Page 2 of 2 PUBLIC UTILITIES STAFF REPORT