HomeMy WebLinkAboutDOT status update- March 23, 2007
Page 1 of 1
From: Troy L. Baker [tlbaker@dot.state.nc.us]
Sent:
Friday, March 23, 2007 4:15 PM
To:
Samantha Ficzko
Cc:
Chris McGee
Subject:
Re: Forest Ridge
Samantha,
Our subdivision review was completed based on the "40" lots. As of now, he has not applied for a
entire
driveway permit. Kimley-Horn is in the process of preparing a TIA for the development. They
have had to do some modifications (i.e.. "super street" design) to meet our criteria for all developments
along that corridor of NC 87. Once the driveway permit has been applied for and approved, we may ask
for assistance from the Planning Department if the requirements for the driveway permit has not been
fulfilled (such as not issuing any further building permits).
Thanks for keeping us up to date...
Troy
Samantha Ficzko wrote:
Troy,
Good morning
We have received a final plat for approval for Forest Ridge, which I am in the process of reviewing.
Generally, the only thing we look for on these plats in regards to DOT is someone’s signature. Since there is a
DOT signature on this plat, we are going to consider that sufficient as far as DOT approval is concerned (ie-
we will likely move to conditionally approve this plat at the DRB meeting next week). Is that okay with you
guys? I attached the plat for you as well.
~Samantha
Thanks and have a great day!
Samantha Ficzko
Planner I
HarnettCounty
PO Box 65
Lillington, NC27546
(910)893-7525, ext. 4
Fax:(910)814-6459