PUBLIC UTILITIES STAFF REPORT
Harnett County, North Carolina
Planning Department
108 E. Front Street, Lillington, NC 27546
Phone: (910) 893-7525 Fax: (910) 893-2793
Development Name: Ballard Woods Phase 4 – Final
Property Description
PIN(s): 0651-39-0029.000 & 0651-39- Acreage: 25.00 acres
5994.000
Address/SR No.: Ballard Road (SR 1437)
Water
Public water is available for this development (via Harnett County)
Water capacity is available for this development
Nearest water line location (Road name & SR#): Joseph Alexander Drive
Nearest water line size: 6”
Fire flow is available for this development
Lines permitted under DENR Permit: 06-01818 (DEH Serial Number)
Sewer
Public sewer is available for this development (via Harnett County)
Sewer capacity is available for this development
Nearest sewer line location (Road name & SR#): 48” Wastewater Interceptor
Lines permitted under DENR Permit: WQ0030976 (DWQ Serial Number)
Additional Requirements
As-Built Record Drawings Yes No N/A
Cost Statement for water improvements Yes No N/A
Cost Statement for sewer improvements Yes No N/A
Professional Engineer’s Certifications for water/sewer extension Yes No
N/A
Final Plat & As-Built Record Drawings are identical Yes No N/A
DOT Encroachment Agreement Yes No N/A
Distance to nearest water/sewer lines noted (Site Plan Only) Yes No N/A
Master Plan submitted for additional phases if intended Yes No N/A
Ballot
REVIEWER: Tim Payseur Date: Jan 15, 2008
VOTE: Conditionally Approve
CONDITIONS:
SHORT TERM:
The Utility Contractor must schedule the final inspection with HCDPU on the water and sewer
lines in Phase 4. The inspection must be completed with satisfactory results before the final
plat for Phase 4 may be approved.
The water lines for this development must be approved by HCDPU and NCDENR before the
water meters may be issued to the lots in Phase 4.
The sewer outfall line for Phase 4 was not installed between Phase 4 and the 48” HC-FV WW
Interceptor. The sewer outfall line should be installed and inspected before the final plat may
be approved. Note: If the easement for this outfall line cannot be acquired by the developer
by making an offer for the said easement at fair market value then the developer should offer
Page 1 of 2 PUBLIC UTILITIES STAFF REPORT
the adjacent property owners 15% above the fair market value. If the easement cannot be
obtained and both offers are refused by the adjacent property owners, then Harnett County
Dept of Public Utilities (HCDPU) will install the outfall line and bill the developer for the project
including the cost of said easements as required per the Director of Public Utilities.
The Professional Engineer should provide HCDPU the PE Certifications on the new water and
sewer line extensions, the As Built Record Drawings as required for the final plat approval.
The developer must provide HCDPU with a cost statement for the water and sewer
improvements.
LONG RANGE:
Please visit www.harnett.org/utilities for more information on the approval process.
The developer must provide HCDPU a one (1) year warranty on the water and sewer lines
installed to serve this development.
Page 2 of 2 PUBLIC UTILITIES STAFF REPORT