HomeMy WebLinkAboutANDERSON CRK 2B SECT 5 DECISION PACKET
DRB DECISION PACKET
Harnett County, North Carolina
Planning Department
108 E. Front Street, Lillington, NC 27546
Phone: (910) 893-7525 Fax: (910) 893-2793
Development Name: ANDERSON CREEK PHASE 2B SECTION 5
Development Type: Major Subdivision Final Plan/Plat
Date: September 3, 2008
The above referenced application
is CONDITIONALLY APPROVED as listed below.
SHORT TERM CONDITIONS, COMMENTS, OR JUSTIFICATIONS
The following conditions are to be rectified prior to obtaining DRB signature and are subject to change during the course of the
meeting.
Fire Marshal (910)893-7580: Put in a temporary turnaround on Anderson Lake Drive.
Conditionally Approve:
E911/Addressing (910)814-2038: RD SIGN FEES TO BE PAID.($35.00)
Conditionally Approve:
Setbacks are noted, so remove setback note above title
Planning Department (910)893-7525:
block.
Conditionally Approve:
Update FIRM panel #.....3720050400J
Update Harnett County signature block with…
I hereby certify that the development hereon has been
granted final approval by the Harnett County Development
Review Board pursuant to the regulations set forth by E-
911 Addressing, Environmental Health, Fire Marshal,
Planning, and Public Utilities of Harnett County, N.C.,
subject to recordation in the Harnett County Office of
Register of Deeds within thirty days of the date below.
_____________________________________________
Development Review Board Chairman Date
Provide a letter from the power company certifying that
street lights will be installed accordingly.
Stabilize the ditches and ensure that they will be free of
sediment, stabilized, and seeded. Or, a surety
performance bond should be submitted to ensure this.
The bond should be made payable to Harnett County and
equal to the amount of 1.25 times the entire cost, as
estimated by the owner/ developer and approved by the
County.
The Utility Contractor must schedule the final inspection with
Public Utilities (910)893-7575:
the HCDPU utility Construction Inspector. If a punch list is
Conditionally Approve:
generated from the final inspection then the punch list items
must be completed before the final plat can be released for
recording.
The Professional Engineer (P.E.) must provide HCDPU with
the As-Built Record drawings and the P.E. Certifications for
the water and sewer improvements installed to serve this
ANDERSON CRK 2B SECT 5 DECISION PACKET
3/13/2009
1
subdivision.
The Developer must provide HCDPU with the Cost Statements for the
water and sewer improvements installed to serve this subdivision.
Environmental Health (910)893-7547:
Approve:
LONG RANGE CONDITIONS
The following conditions must be satisfied
Must meet all requirements set forth by NC DENR. Contact at (910)433-3300.
Public Utilities (910)893-7575: The Developer must provide Harnett County with a one (1) year
warranty on the water and sewer improvements installed to serve this
subdivision.
:
:
:
:
Development Review Board
Chairman
If APPROVED, your signed plat/plan may be picked up at the Planning Department or will be mailed to you within two (2)
business days.
If APPROVED WITH CONDITIONS, you must submit 5 copies of the plat/plan to the Planning Department showing that all
items listed under Short Term Conditions have been rectified. Please be aware that review will not be done while you wait,
as all DRB members will have to review the plat/plan for compliance.
If HELD, you must submit 5 copies of the plat/plan showing that all items listed under Short Term Conditions have been
rectified. To attend the next DRB meeting, revised plat/plans must be submitted by noon on Wednesday following the
meeting the application was put on hold.
If DENIED, you may appeal the Board’s Decision to the Harnett County Planning Board within 30 days or meet with
Planning Staff to discuss other potential options.
ANDERSON CRK 2B SECT 5 DECISION PACKET
3/13/2009
2