BUILDING Plan Box Number [. 3 Job Name (e-&o k w c
Date: in- Z $- 1 l
Required Inspections for SFA/SFD _
Appl.# J6 SW 32144 1
Valuation-1 ZO 3 1 61
Sq.Feet .3 12-
Sequence
10 ✓ R* Bldg. Footing
10 -30 R* Elec. Temp Service Pole
20 ✓ R* Building Foundation
20 Address Confirmation
30 -999 ,% Open Floor
30 -999 R* Bldg. Slab Insp.
30 -999 R* Elec. Under Slab
30 -999 R *Plumb. Under Slab
40 IP Four Trade Rough In
40 ✓ Four Trade Rough In> 2500
40 Three Trade Rough In
40 Three Trade Rough In> 2500
40 Two Trade Rough In
40 Two Trade Rough In> 2500
40 One Trade Rough In
40 One Trade Rough In > 2500
50 ✓ R* Insulation
60 Four Trade Final
60 ✓ Four Trade Final > 2500
60 Three Trade Final
60 Three Trade Final > 2500
60 Two Trade Final
60 Two Trade Final > 2500
60 One Trade Final
60 One Trade Final > 2500
999 Envir. Operations Permit
Plan Box Number C 3 Job Name Co.A..0 i u C sac
Date: In - Z $ - 1-
Required Inspections for SFA /SFD
Appl.# 10 5602Sy4
Valuatioi3 ZO 3 1 61
Sq. Feet 3 2 P
Sequence
10 R* Bldg. Footing
10 -30 R* Elec. Temp Service Pole
20 ✓ R* Building Foundation
20 Address Confirmation
30 -999 ✓ Open Floor
30 -999 R* Bldg. Slab Insp.
30 -999 R* Elec. Under Slab
30 -999 R *Plumb. Under Slab
40 Four Trade Rough In
40 Four Trade Rough In> 2500
40 Three Trade Rough In
40 Three Trade Rough In> 2500
40 Two Trade Rough In
40 Two Trade Rough In> 2500
40 One Trade Rough In
40 One Trade Rough In > 2500
50 ✓ R* Insulation
60 Four Trade Final
60 ✓ Four Trade Final > 2500
60 Three Trade Final
60 Three Trade Final > 2500
60 Two Trade Final
60 Two Trade Final > 2500
60 One Trade Final
60 One Trade Final > 2500
999 Envir. Operations Permit